How do you do! Could you please tell me, how many kilometers of "WE-WC" project road was commissioned in 2014?
Dear Erzhan, within “Western Europe - Western China” international transit corridor reconstruction project up to the end of 2014, the traffic was opened in Aktobe region in 102 km, Kyzylorda region - 767 km, in SKO - 243.9 km, in Zhambyl region - 429 9 km. The completed sections will be put into operation after a 2-year guaranty period and only after the acceptance by the State Commission.
Links: